Mitigation bank in the path sends the Outer Loop's SH 121-to-US 380 leg back for new routes

Collin County engineers want a $982,008.50 contract change so HDR can draw alignments that avoid protected wetland credits. A third public meeting would follow this winter.

Gwen Lindgren· AI-assisted, edited by Jake Team

November 6, 20262 min read

Route Planning - illustration, Jake Team LLC

Collin County's planned Outer Loop segment between State Highway 121 and U.S. 380 is headed back to the drawing board, after county staff learned two of its candidate routes would cut through a federally overseen wetland mitigation bank.

Commissioners on Monday, Nov. 9, are scheduled to consider Amendment No. 1 to the county's engineering contract with HDR Engineering, Inc. for the segment, known as Segment 5. The change would add $982,008.50 so the firm can study more alignments and prepare a local environmental document, according to a Nov. 2 memo from Assistant Director of Engineering Tracy Homfeld.

What changed

The county has held two public meetings on route choices: a virtual meeting from Nov. 13 to Dec. 15, 2025, which drew more than 300 comments, and in-person sessions June 3 and 4, which drew more than 240, according to a staff presentation in the court packet. Comments centered on cost, eminent domain, property effects and agriculture.

A comment at the June meetings pointed staff to the Arnold Creek Mitigation Bank, which includes the Lone Oak and Indian Creek tracts. The presentation lists the remaining alignments' effects on the bank at 22.5 acres for the Dark Blue route, identified as technically preferred in 2007, 22.4 acres for Pink and 61.9 acres for Green. An Orange route was dropped after the second meeting.

Blue Ridge passed a resolution opposing Green over its effects on Blue Ridge School and a wastewater plant, and Farmersville opposed Green and Orange as redundant with SH 78.

The U.S. Army Corps of Engineers recommended avoiding the bank, the presentation says. A route through it would need an individual federal permit, which staff warned could hold up right-of-way purchases for three years or more and could still be denied. Staff put the possible cost of offsetting the bank effects at about $9 million to $30.5 million.

New schedule

If commissioners approve the amendment, the memo lays out this timeline:

  • Third public meeting on new alternatives: December 2026 or January 2027
  • Commissioners Court hearing on a new preferred alignment: February or March 2027
  • Draft local environmental document: September 2027
  • Final adoption: November 2027, with right-of-way mapping in December 2027

Some parcels could be mapped as early as late summer 2027 once archaeological and water resource surveys are done, if no environmental effects turn up, the memo says. The money is already in the project's consultant account.

Sources

eagenda.collincountytx.gov

eagenda.collincountytx.gov

eagenda.collincountytx.gov

eagenda.collincountytx.gov

Share

Gwen Lindgren· AI-assisted, edited by Jake Team

Gwen Lindgren writes about community life, schools, public safety, and local events in Melissa.

Related Stories

More in Texas