Outer Loop route between SH 121 and U.S. 380 gets a redo after environmental concerns, with a third public meeting planned

Collin County would pay HDR Engineering $982,008 more to study new alignments for the 21-mile Segment 5 and write an environmental document. A preferred route would not go to commissioners until late winter 2027.

Gwen Lindgren· AI-assisted, edited by Jake Team

October 19, 20262 min read

Survey stakes in field - illustration, Jake Team LLC

Collin County's engineers want another look at where the Outer Loop should run between State Highway 121 and U.S. 380, and under a new schedule a preferred route for that stretch would not reach commissioners for a public hearing until late winter 2027.

A contract change on the county's agenda for its Nov. 2 Commissioners Court meeting would pay HDR Engineering $982,008.50 for more route and environmental work on Segment 5 of the Collin County Outer Loop. The added work would bring HDR's contract to $5,077,646.83.

Why the extra study

Two public meetings have already been held on route options for the segment. After the second one, the county received information identifying environmental constraints that need more evaluation, according to a memo from Assistant Engineering Director Tracy Homfeld. The memo does not describe the constraints.

As a result, HDR would evaluate more alignment options and hold another public meeting before recommending a final route. The county also wants HDR to prepare a Local Environmental Document, which the scope says would support the county's ability to buy right of way.

What the study covers

The scope describes Segment 5 as about 21 miles long, running from SH 121 to U.S. 380 on the east side of Farmersville. The study area reaches from SH 121 east to the Hunt County line, and from U.S. 380 north to the Fannin and Grayson county lines.

HDR would start from the two alternatives shown at the second public meeting, labeled Pink and Green, and could draw up to three modified versions. No new end-to-end routes would be developed, the scope says.

The environmental work includes archaeological and historical reviews, threatened and endangered species checks, hazardous materials screening and a water resources survey. Creeks named for possible field surveys include Sister Grove, Pilot Grove, Indian, Desert, Pot Rack, Red Oak and Elm creeks, among others.

Crews would need permission to enter private land, and the scope calls for the county to send right-of-entry letters to owners, with two attempts per property before it is marked access denied.

Anna, Melissa, Blue Ridge and Farmersville are listed among the stakeholders for up to four small-group meetings, along with TxDOT, the North Central Texas Council of Governments and school districts.

Timeline

The memo lays out this schedule:

  • Third public meeting to show new alternatives: early winter 2026
  • Commissioners Court public hearing on a new preferred route: late winter 2027
  • Draft environmental document for staff review: fall 2027
  • Commissioners Court adoption of the final environmental document, and right-of-way mapping: winter 2027

Some right-of-way mapping could move up to the end of summer 2027 if the archaeological and water surveys find no environmental problems, the memo says. Staff also plan to brief commissioners on the alignment study.

Sources

eagenda.collincountytx.gov

eagenda.collincountytx.gov

eagenda.collincountytx.gov